RFP ADDENDUM # 3
Question and Answer
Does the Jersey City Redevelopment Agency plan to issue an RFP for the parking lot on 1st Street?
No.
RFP ADDENDUM # 3
Question and Answer
Does the Jersey City Redevelopment Agency plan to issue an RFP for the parking lot on 1st Street?
No.
PUBLIC NOTICE
THE JERSEY CITY REDEVELOPMENT AGENCY BOARD OF COMMISSIONERS MEETING FOR AUGUST 15, 2023
PLEASE BE ADVISED THAT THE BOARD OF COMMISSIONERS OF THE JERSEY CITY REDEVELOPMENT AGENCY WILL HOLD ITS REGULARLY SCHEDULE MEETING ON TUESDAY, AUGUST 15, 2023 AT 6:00 P.M. IN PERSON, LOCATED AT EXPLORER MIDDLE SCHOOL LOCATED AT 180 NINTH STREET, JERSEY CITY, NEW JERSEY. AGENDA WILL INCLUDE: ADOPTION OF MINUTES OF PREVIOUS MEETING; FINANCIAL MATTERS; PERSONNEL MATTERS; AND OTHER GENERAL BUSINESS OF THE AGENCY OR MATTERS THAT MAY COME BEFORE THE BOARD. OFFICIAL ACTION MAY BE TAKEN.
August 9, 2023
Jesamil Lozano
Secretary to the Board
NOTICE TO ALL POTENTIAL RESPONDENTS
The Request for Proposals for Acquisition and Redevelopment of 244 Bay Avenue (the “RFP”) is modified as set forth in this Addendum (Addendum #2). The RFP and Addendum #1 remain in full force and effect, except as modified by Addendum #2, which is hereby made part of the RFP. Respondent shall take Addendum #2 into consideration when preparing and submitting its Proposal.
RFP ADDENDUM # 2
Section V of the RFP is replaced as follows:
The Agency seeks development submissions which achieve the goals of the Redevelopment Plan, maximize the Redevelopment Site’s potential and benefit and complement the surrounding area. Specifically, the Agency seeks proposals for the Redevelopment Site which address one or more of the following:
NOTICE TO ALL POTENTIAL RESPONDENTS
The Request for Proposals for Acquisition and Redevelopment of 244 Bay Avenue (the “RFP”) is modified as set forth in this Addendum. The RFP remains in full force and effect, except as modified by this Addendum, which is hereby made part of the RFP. Respondent shall take this Addendum into consideration when preparing and submitting its Proposal.
RFP ADDENDUM # 1
Section IV of the RFP is amended as follows:
The Agency will host a non-mandatory visit at the Redevelopment Site on August 2, 2023 at 10:00am. The Agency will also schedule visits at the Redevelopment Site for Respondents upon request. Site visit requests shall be sent to Yvette Sanchez, Agency Project Manager at YSanchez@jcnj.org and Robert Napiorski, Agency Project Manager at RNapiorski@jcnj.org. No site visits will be scheduled after Thursday August 31, 2023.
Section VII of the RFP is amended as follows:
The following dates shall apply to the RFP response process.
| Issuance of RFP | July 24, 2023 |
| Non-mandatory site visit |
August 2, 2023 at 10:00am or upon request as provided in Section IV
|
| RFP Questions Due | August 16, 2023 |
| Agency Responses to RFP Questions Posted on Agency Website | August 23, 2023 |
| RFP Submission Due to the Agency | September 12, 2023 |
REQUEST FOR PROPOSALS:
Acquisition and Redevelopment of 244 Bay Street within the 244 Bay Street Rehabilitation Area
PLEASE BE ADVISED THAT THE BOARD OF COMMISSIONERS OF THE JERSEY CITY REDEVELOPMENT AGENCY WILL HOLD A SPECIAL MEETING ON MONDAY, JULY 24, 2023 AT 6:00 P.M. AT EXPLORER MIDDLE SCHOOL LOCATED AT 180 NINTH STREET, JERSEY CITY, NEW JERSEY
JERSEY CITY REDEVELOPMENT AGENCY
Economic Impact Study RFP
Questions and Answers
Centre Pompidou x New Jersey Museum
June 16, 2023
1. Can companies outside the USA apply for this? (i.e., from India or Canada)
Yes. Pursuant to N.J.S.A. 52:32-44, all contractors and subcontractors must provide a Business Registration Certificate from the New Jersey Division of Revenue in the Department of Treasury when doing business with the State of New Jersey, and other public agencies in the State of New Jersey.
2. Will we need to come to Jersey City for meetings?
It is anticipated that some meetings will take place in-person in Jersey City and some may take place in Trenton or other locations in the State of New Jersey.
3. Can we perform the tasks (related to RFP) outside the USA? (i.e., from India or Canada)
Yes, unless otherwise specified by the Agency.
4. Can we submit the proposals via email?
Yes, per page 10, section 3.1.1, proposals can be submitted via email to Rob Napiorski (RNapiorski@jcnj.org) and Cortez Crosby (ccrosby@paratusgroup.com).
5. Are assumptions regarding attendance, visitor spending at museum, personnel plan, and operating budgets in place and available as the basis for the economic impact study?
These assumptions are not in place or available.
6. If not, does the economic impact assignment include preparation of such fundamental assumptions with the idea that these assumptions would then be refined and detailed in 2.2 Additional Scope of Work-Business Operating Plan?
Yes.
7. Will the economic impacts analysis then be refined to reflect the results of Task 2.2?
Yes.
8. Is the intent of 2.1.3 to develop an estimate of new development due to the new museum, or to evaluate the impacts of planned developments that have been proposed or planned?
The intent is to evaluate the impacts of both the new museum and the developments that have been proposed or planned.
9. Will Task 1 (economic impacts) and Task 2 (business and operating plan) be contracted at project outset?
One contract will be executed at project outset with Task 2 included as an Additional Service to be initiated upon written authorization from JCRA.
10. What is the target completion date for Task 1 and for Task 2?
JCRA will rely on the successful candidate to provide a workplan and meeting schedule to complete these tasks in a timely manner. Respondent should indicate approximately how long it will take to complete each task
11. Has a target budget been established for Task 1 and for Task 2? If so, what are these budgets?
No.
12. Has a targeted number of meetings been established for Task 1 and for Task 2? If so, how many?
JCRA will rely on the successful candidate to provide a workplan and meeting schedule to complete these tasks in a timely manner. In addition, the successful respondent may be required to attend meetings with the Agency regarding the services being provided.
13. Are the desired 2.2.5 (c) templates to be provided in Excel format?
Yes. Excel is an acceptable format.
14. Will the consultant have access and work with the development team regarding assumptions of potential contributed and endowment funds?
Yes, JCRA and the State of New Jersey will share assumptions about budgets and potential contributed funds as they develop. Currently, a development team is not in place.
15. Will the consultant have access to the engineering team to determine appropriate allowances for utilities?
Yes.
16. Will the off-site offices be defined in program of spaces to inform estimates regarding this component of the plan?
Yes.
17. Is a marketing team available for interface regarding the marketing and audience development aspects of the plan?
Currently, there is not a marketing team in place. Jersey City and Pompidou are in the early stages of developing coordinated strategies for marketing and audience development.
18. Can we receive electronic editable proposal forms? It seems the ones in the RFP are scanned docs and we are unable to edit.
No.
19. Do subcontractors need to fill out all forms with proposal submittal?
Yes.
20. Will a site visit take place?
There will not be a site visit during the procurement process. As part of the onboarding process with the successful respondent, a neighborhood and building walk will be scheduled. In the meantime, we encourage potential respondents to visit the Journal Square area to get a sense of the development occurring in that area.
PUBLIC NOTICE
THE JERSEY CITY REDEVELOPMENT AGENCY BOARD OF COMMISSIONERS MEETING FOR JUNE 20, 2023
PLEASE BE ADVISED THAT THE BOARD OF COMMISSIONERS OF THE JERSEY CITY REDEVELOPMENT AGENCY WILL HOLD ITS REGULARLY SCHEDULE MEETING ON TUESDAY, JUNE 20, 2023 AT 6:00 P.M. IN PERSON, LOCATED AT EXPLORER MIDDLE SCHOOL LOCATED AT 180 NINTH STREET, JERSEY CITY, NEW JERSEY. AGENDA WILL INCLUDE: ADOPTION OF MINUTES OF PREVIOUS MEETING; FINANCIAL MATTERS; PERSONNEL MATTERS; AND OTHER GENERAL BUSINESS OF THE AGENCY OR MATTERS THAT MAY COME BEFORE THE BOARD. OFFICIAL ACTION MAY BE TAKEN.
June 14, 2023
Jesamil Lozano
Secretary to the Board
PUBLIC NOTICE
THE JERSEY CITY REDEVELOPMENT AGENCY BOARD OF COMMISSIONERS MEETING FOR MAY 16, 2023
PLEASE BE ADVISED THAT THE BOARD OF COMMISSIONERS OF THE JERSEY CITY REDEVELOPMENT AGENCY WILL HOLD ITS REGULARLY SCHEDULE MEETING ON TUESDAY, MAY 16, 2023 AT 6:00 P.M. IN PERSON, LOCATED AT EXPLORER MIDDLE SCHOOL LOCATED AT 180 NINTH STREET, JERSEY CITY, NEW JERSEY. AGENDA WILL INCLUDE: ADOPTION OF MINUTES OF PREVIOUS MEETING; FINANCIAL MATTERS; PERSONNEL MATTERS; AND OTHER GENERAL BUSINESS OF THE AGENCY OR MATTERS THAT MAY COME BEFORE THE BOARD. OFFICIAL ACTION MAY BE TAKEN.
May 10, 2023
Jesamil Lozano
Secretary to the Board
Questions and Answers for Property Rehabilitation Services RFB at
405 – 407 Ocean Avenue
April 24, 2023
Q. Is the project PLA or non-union?
A. It is PLA. The successful bidder will be required to comply with New Jersey’s Prevailing
Wage Act.
Q. Is the 407 Ocean Avenue portion of the property substantially the same as 405 Ocean
Avenue portion?
A. Yes, the layout is the mirror of 405 Ocean Avenue.
Q. Can another site visit be arranged, as 407 Ocean Ave. portion of the property was
inaccessible?
A. Yes, another site visit can be arranged.
Q. Is there an additional process other than the Request for Bid from the Jersey City
Redevelopment Agency?
A. No, this is the only process required to bid on this project.